Case Study: Rescuing a Mid-Flight Salesforce Org Consolidation
I picked up a $484,838 time-and-materials Salesforce consolidation partway through. The previous PM had left no project plan and no budget tracking. In week one, I got our team and the client in the same room and built a real plan from their own dependency map. Then I sent daily updates until the client trusted the project again. We merged three Salesforce orgs into one, with CPQ and a NetSuite integration, held the original go-live date, and had minimal post-launch defects.

Situation
A U.S. financial-technology firm had grown by acquiring two competitors and was still running three separate Salesforce orgs. The engagement: merge them into one, stand up CPQ, and integrate NetSuite, all on a time-and-materials contract with no budget guarantee.
Stakes
The SOW put all data cleansing, dedup, and error resolution on the client's plate, and only a sample migration was ever tested before go-live. The real cutover was a single, multi-day production load with no rehearsal budgeted. Get it wrong, and a company running its business on that org loses live sales and service data.
Diagnosis
The previous PM had left no project plan and no real budget tracking, and that gap needed fixing before anything else could move. Next was schedule: were there dates already promised to the client on any workstream that a new plan had to protect? And underneath the migration itself: what actually had to happen, and in what order, before the data could move at all?
Decision
Got the internal team and the client in the same room to lay out what was done, what was left, and what depended on what. That session became the skeleton of a real project plan, with the open dependencies turned into concrete action items instead of open questions.
Action
Ran discovery across the three legacy orgs to define the consolidated data model, managed the T&M budget and scope conversation with the client throughout, and coordinated the single production cutover, using Gearset for metadata and Data Loader for records, along with the post-deployment support window.
Result
The field-mapping working session with the client turned out to be the dependency that mattered most. It's what made the migration go smoothly. With no slack in the schedule left by the prior PM, the team ran the cutover across several evenings and a weekend to hit the date that had already been set before I joined, but defects came in minimal. On budget, the missing tracking from the earlier PM meant a change order was unavoidable. I negotiated it so we absorbed part of the added cost rather than passing all of it through to the client.
- Migration completed with minimal post-launch defects
- Original go-live date held despite inherited schedule slippage
- Change order negotiated with cost shared, not passed through in full
Trust gets rebuilt in daily updates, not in the final deliverable.
Taking over a project that's already gone sideways means changing how you communicate before you change anything else: sympathetic about where the client's frustration comes from, upfront about where things actually stand, the risks, the issues, and the plan to close them. Daily end-of-day updates and a daily morning sync with the client's product manager, for a couple of weeks, until the updates weren't necessary anymore because the trust was already there. None of that works without getting the full picture first, from your own team and from the client, before it's your risk register to keep.